Enterprise Systems Integration for a Global Pharmaceutical Company
Duration: March – July 2026 (~4 months)
Customer location: Belgium
● Australia
The client
A global pharmaceutical enterprise specializing in oncology treatments, operating across several regional entities with core stakeholders in Belgium and Australia. The engagement centered on an internal tool for project and resource management, separate from the company’s clinical work — helping their project managers plan workload and capacity across a large, distributed organization.
Why the client chose Ralabs
The client ran a vendor selection process for a capacity-management tool. Once the platform was chosen, they needed the systems integration services the tool didn’t provide — and were introduced to Ralabs through a trusted partner in the resource-management space.
Two criteria drove the decision: fit-for-purpose and simplicity — avoiding an over-engineered, heavily customized solution — alongside cost. A more powerful competing approach had already been rejected for being too complex and expensive relative to the value it added.
The challenge
The client’s project managers relied on three to five disconnected tools to plan work and manage people. The same underlying data lived in separate systems, so every change had to be reconciled by hand — often by emailing colleagues across time zones.
Key challenges included:
No single source of truth
Project and resource data were spread across MS Project, Smartsheet, and Azure/Entra. Nothing kept them aligned, so managers had no reliable, unified view of who was working on what.
Automating a legacy desktop application
MS Project is a legacy desktop app with no vendor support and slated for deprecation, offering no easy way to automate or integrate with it. Reliably extracting its data meant writing VBA macros as a mandatory dependency — the technical obstacle.
A specialized legacy-scripting knowledge gap
Automating MS Project meant writing VBA macros — a dated, rarely used scripting approach the team wasn’t an expert in. They closed the gap by using AI to help author and troubleshoot the VBA the integration required — an approach that shows how Ralabs handles legacy system modernization.
Coordinating a large, distributed enterprise
Stakeholders spanned multiple countries and time zones, and enterprise processes moved deliberately. Keeping scope, decisions, and delivery aligned required disciplined project management throughout.
What was done
Ralabs built an event-driven data integration pipeline in n8n (an open-source workflow automation tool) that connects the client’s four core systems and keeps resource data synchronized automatically. When an assignment changes, the update now propagates to the central planning tool — either on a schedule or when a manager triggers a data consolidation — with no manual reconciliation.
Discovery and scoping
Mapped the four source systems and defined how project and resource data should flow between them.
MS Project connectivity
Built a VBA macro and configured an n8n source connector to extract task-level scheduling data from the legacy desktop application.
Source system integration
Connected Azure/Entra (resource data) and Smartsheet (portfolio system of record) through custom API integration development.
Data mapping and transformation
Standardized incoming data into a single model and routed it to Runn, the central capacity-planning platform.
Nominative and generic resource handling
Supported both named individuals and role-based placeholders (e.g. “Quality Associate”) used for early-stage planning.
Validation and error handling
Routed invalid assignment packages out of the flow for review, so bad data never reaches the target system.
Delivery cadence
Led weekly technical and core team meetings to review potential risks and blockers, align on the project roadmap and milestone timelines, and prepared weekly project status reports through UAT and Go-Live.
Implemented features:
Event-driven sync pipeline
A webhook listener triggers the workflow, which can also run on a schedule or on manual demand. Resource allocation propagates to Runn automatically, replacing manual updates.
Legacy MS Project connector
A purpose-built VBA macro and n8n Webhook handle the legacy system integration — extracting scheduling data from the unsupported desktop application and bringing previously siloed project data into the pipeline.
Multi-system aggregation
Smartsheet, Azure/Entra, and MS Project feed a single consolidation flow, giving managers one accurate view of people and projects without contacting anyone.
Nominative and generic resource mapping
The pipeline maps named individuals and creates role-based placeholders, so teams can forecast workload and demand before specific people are assigned.
Assignment validation and routing
Invalid assignment packages are automatically separated for error handling, keeping the target system clean and reliable.
How the collaboration worked
The team worked in a lightweight, Kanban-style flow suited to an integration project, delivering in increments.
Communication ran on a steady weekly rhythm across two standing calls:
- A technical call with Ralabs’ engineers and the client’s technical stakeholders.
- A core-team / roadmap call covering timeline, blockers, and action items across all stakeholders.
Alongside the calls, the project manager maintained a set of delivery artifacts: a weekly roadmap, an action-items list, and weekly reports on risks, blockers, completed scope, next priorities, and any actions pending on the client’s side. A risk register, risk-review sessions, and a RACI matrix were established early, with ad-hoc check-ins as needed. The engagement ran on a fixed-price contract.
Results:
Resource updates now propagate automatically across four systems. Managers no longer email colleagues across time zones to keep records aligned.
Project and resource data now consolidate into a single planning view, replacing three-to-five disconnected tools.
Scope was adapted to evolving requirements while holding to the agreed commercial terms.
With projects unified in one system, replacing the deprecated legacy tool later will be substantially simpler.
What the team has to say
Andriana
Project Manager
“It was a valuable experience working with an enterprise-level client, where the team consistently built a strong working relationship and received positive feedback throughout the engagement while proactively addressing evolving requirements. I also appreciated the opportunity to work with Microsoft Project ecosystem tools, further strengthening my ability to adapt quickly to client-specific project management and collaboration environments”.
Aleksandar
Integration Engineer
“We enjoyed this project and learned a lot. Working with legacy technology inside a large enterprise environment sharpened how we scope and approach the next integration like it”.
Tech stack
Working directly with Ralabs’ engineers made everything faster and easier — the flexibility to skip the usual process layers was a real advantage.
Client
Technical lead
Other сases
Team size: 11 developers
Team size: 6 developers
Team size: 7 developers
Team size: 5 developers
Team size: 3 developers
Team size: 5 developers